Discos

Value for Money (DisCo Ranking)
April 19, 2021 - April 25, 2021
Disco Ranking
Abuja Electricity Distribution 10
Benin Electricity Distribution 6
Eko Electricity Distribution 3
Enugu Electricity Distribution 9
Ibadan Electricity Distribution 4
Ikeja Electricity Distribution 1
Jos Electricity Distribution 7
Kaduna Electricity Distribution 5
Kano Electricity Distribution 11
Port Harcourt Electricity Distribution 8
Yola Electricity Distribution 2

IWIN Editorials


Daily Energy Watch

05-05-2021 07-05-2021
Available Generation Capability MW 5475.70 5224.00
Peak Generation MW 5037.30 4890.50
Average Generation MW 4607.43 4470.72
Generation Constraint due to Gas MW 1576.50 1703.70
Generation Constraint due to Water MW 538.30 581.30
Generation Constraint Due to Load Rejection MW 25.00 521.00
Generation Constraint Due to Transmission MW 0.00 0.00
Total Constrained Generation MW 2139.80 2806.00