Charts


Hours
Discos

Value for Money (DisCo Ranking)
March 29, 2021 - April 04, 2021
Disco Ranking
Abuja Electricity Distribution 9
Benin Electricity Distribution 5
Eko Electricity Distribution 3
Enugu Electricity Distribution 7
Ibadan Electricity Distribution 4
Ikeja Electricity Distribution 1
Jos Electricity Distribution 6
Kaduna Electricity Distribution 8
Kano Electricity Distribution 10
Port Harcourt Electricity Distribution 11
Yola Electricity Distribution 2

IWIN Editorials


Daily Energy Watch

09-04-2021 10-04-2021
Available Generation Capability MW 7542.40 7709.90
Peak Generation MW 4092.50 4897.00
Average Generation MW 3527.88 3774.96
Generation Constraint due to Gas MW 1520.00 1559.00
Generation Constraint due to Water MW 240.00 160.00
Generation Constraint Due to Load Rejection MW 1859.00 1509.00
Generation Constraint Due to Transmission MW 171.20 42.70
Total Constrained Generation MW 3790.20 3270.70
Available Generation Capability MW 5605.40 5514.40
Peak Generation MW 4908.90 4700.50
Average Generation MW 4263.85 4407.67
Generation Constraint due to Gas MW 1787.30 1758.60
Generation Constraint due to Water MW 504.10 507.10
Generation Constraint Due to Load Rejection MW 92.00 565.00
Generation Constraint Due to Transmission MW 0.00 0.00
Total Constrained Generation MW 2383.40 2830.70