Charts


Hours
Discos

Value for Money (DisCo Ranking)
July 06, 2020 - July 12, 2020
Disco Ranking
Abuja Electricity Distribution 9
Benin Electricity Distribution 7
Eko Electricity Distribution 3
Enugu Electricity Distribution 11
Ibadan Electricity Distribution 4
Ikeja Electricity Distribution 1
Jos Electricity Distribution 8
Kaduna Electricity Distribution 5
Kano Electricity Distribution 2
Port Harcourt Electricity Distribution 10
Yola Electricity Distribution 2

IWIN Editorials


Daily Energy Watch

19-07-2020 02-08-2020
Available Generation Capability MW 7542.40 7709.90
Peak Generation MW 4092.50 4897.00
Average Generation MW 3527.88 3774.96
Generation Constraint due to Gas MW 1520.00 1559.00
Generation Constraint due to Water MW 240.00 160.00
Generation Constraint Due to Load Rejection MW 1859.00 1509.00
Generation Constraint Due to Transmission MW 171.20 42.70
Total Constrained Generation MW 3790.20 3270.70
Available Generation Capability MW 5835.80 5891.80
Peak Generation MW 4808.70 4819.00
Average Generation MW 3830.10 3989.41
Generation Constraint due to Gas MW 0.00 0.00
Generation Constraint due to Water MW 0.00 0.00
Generation Constraint Due to Load Rejection MW 2037.80 2731.40
Generation Constraint Due to Transmission MW 0.00 0.00
Total Constrained Generation MW 2037.80 2731.40

Successor Comapanies